Resource Management Questions
Configure and manage resource allocation, capacity planning, and team assignments across projects.
Newest question added: AI-assisted drafts, not yet individually reviewedHow questions are made
About Resource Management
Resource Management ensures the right people are assigned to the right work at the right time. It includes capacity planning, allocation, and utilization tracking.
Why This Matters for Your Exam
Resource Management covers 23% of the CIS-SPM exam. Effective resource management is critical for project success.
Key Concepts to Master
Master resource pools, allocation methods, and capacity planning. Understand how to manage over/under allocation and resource conflicts.
Exam Tips
Focus on resource allocation mechanisms, capacity calculations, and conflict resolution. Know the different allocation methods and when to use each.
Practice Questions
15 questions availableA resource manager reviews a submitted resource plan for an upcoming demand and blocks the requested resources, creating soft allocations but not yet hard allocations. Which state is the resource plan in now?
👆 Click an option above to select your answer
Show answer and explanation
Correct answer: A. Confirmed
After a plan is requested, the resource manager can block or confirm the resources for future projects and demands, which moves the plan to the Confirmed state. Soft allocations are created at this point; they become hard allocations only when the plan moves to Allocated.
- Why B is wrong: In the Allocated state soft allocations are converted to hard allocations, which has not happened yet here.
- Why C is wrong: Planning is the default state when the requester creates the plan, before it is submitted.
- Why D is wrong: Requested is the state after the requester submits the plan for review, before the resource manager confirms resources.
A new engineer has joined a delivery group, but a project manager cannot find the engineer when building a resource plan. Which role must the engineer have to be considered for resource planning?
👆 Click an option above to select your answer
Show answer and explanation
Correct answer: C. pps_resource
Only users with the PPS resource [pps_resource] role are considered for resource planning, and only users or groups with that role appear in resource plans. Granting pps_resource to the engineer makes them available to resource plans.
- Why A is wrong: resource_user is the requester role used to create resource plans and request resources; it does not make a person a plannable resource.
- Why B is wrong: timecard_user lets a user create time cards for themselves; it does not control resource plan eligibility.
- Why D is wrong: resource_manager is used to review resource plans and confirm and allocate resources, not to be planned as a resource.