Project Management Questions

Master project creation, planning, execution, and monitoring within the SPM framework.

19 total questions2 free questions

Newest question added: AI-assisted drafts, not yet individually reviewedHow questions are made

About Project Management

Project Management in SPM provides comprehensive tools for planning, executing, and tracking projects. It includes task management, milestone tracking, and integration with resource and financial management.

Why This Matters for Your Exam

Project Management is the largest domain at 30% of the CIS-SPM exam. This reflects its central role in SPM.

Key Concepts to Master

Understand project templates, WBS creation, task dependencies, and project status tracking. Know how projects integrate with resource and financial management.

Exam Tips

Focus on project creation methods, task management, and status reporting. Know how to use the project workbench and understand project health indicators.

Practice Questions

19 questions available
1
application

On a project, the testing task must not start until the development task has started. Which dependency type should the project manager create between the development task (predecessor) and the testing task (successor)?

AFinish-to-start
BFinish-to-finish
CStart-to-start
DStart-to-finish

👆 Click an option above to select your answer

Show answer and explanation

Correct answer: C. Start-to-start

A start-to-start dependency indicates that a successor task must not be started until the predecessor task has started. Testing can therefore begin once development is underway, without waiting for development to finish.

  • Why A is wrong: Finish-to-start would hold testing until development finishes, which is stricter than the requirement.
  • Why B is wrong: Finish-to-finish links the finish dates of the two tasks, not the start of the successor.
  • Why D is wrong: Start-to-finish constrains when the successor can finish, not when it can start.
2
application

Several project tasks have slipped. The project manager wants the Gantt chart to show a line for each task's original planned start and end dates so the severity of the delays is visible. What should have been created?

AA milestone
BA rollup task
CLag time
DA baseline

👆 Click an option above to select your answer

Show answer and explanation

Correct answer: D. A baseline

A baseline is a snapshot of the planned start and end dates of each task at the time it is created. A line appears under each task on the Gantt chart for those original dates, so when tasks slip the baseline indicator shows how severe the delays are.

  • Why A is wrong: A milestone is a zero-duration task used to indicate an important date, not a snapshot of original task dates.
  • Why B is wrong: A rollup task is a parent task that aggregates child task values such as effort; it does not show original planned dates.
  • Why C is wrong: Lag time is a manually specified gap between a predecessor and successor task; it does not record original dates.